| 2025-10-20 00:00:00Z | | Campbell Met Tower and sensor shipment arrived in Ghana. |
| 2026-03-18 00:00:00Z | Klubi Kwasi | OMI Tower installed. |
| 2026-04-19 15:00:00Z | Emerson HasbrouckBen Greenwood | OMI Tower installation complete; CR6 running Ghana_Tower_20260416.cr6. CELL215 not yet working. |
| 2026-05-12 15:00:00Z | Ben Greenwood | CELL215 modem one-way communication now working from the tower to WHOI. |
| 2026-05-13 12:00:00Z | Ben Greenwood | OMI Tower real-time website created. |
| 2026-06-03 00:00:00Z | | Solar panels were not sufficiently charging the lead-acid battery. The Campbell system was powering down in the evenings. |
| 2026-06-26 12:30:00Z | Klubi Kwasi | Replaced the lead-acid battery with a new lead-acid VRLA 12V-33Ah battery. |
| 2026-07-30 12:00:00Z | Emerson Hasbrouck | CELL215 modem configured for two-way communication. |
| 2026-07-30 13:00:00Z | Ben Greenwood | CR6 code updated remotely: Ghana_Tower_20260730.cr6. |
| 2026-07-30 16:18:00Z | Emerson Hasbrouck | Replaced the RMY Wind Monitor with a new 05108 Wind Monitor + Compass and fixed the PRC wiring issue. |
| 2026-08-04 08:00:00Z | Emerson Hasbrouck | Replaced lead-acid battery with a new VRLA 12V-35Ah battery. |
| 2026-08-04 13:00:00Z | Emerson Hasbrouck | Replaced the faulty Vaisala PTB110 and configured the CH201 charge controller. |
| 2026-08-05 13:30:00Z | Tom Farrar | Solar panel repositioned to increase sunlight; improvement noted in real-time data. |
| 2026-08-07 08:20:00Z | Tom Farrar | Solar panel repositioned to increase sunlight. |